Delevan Compressor Station, K-2 Replacement

Contact Us




Delevan Compressor Station, K-2 Replacement

Client Processes Unlimited International, Inc.
Location Delevan, CA
Scope Of Work Cost estimating, Cost development, Schedule risk analysis
Schedule 2008

Project Detail


Spire provided cost estimating and schedule risk analysis services for Pacific Gas and Electric’s K-2 Compressor Replacement Project at the Delevan Compressor Station in Delevan, California. Spire developed a preliminary cost estimate and supporting basis of estimate in accordance with the Association for Advancement of Cost Engineering International’s (AACEI) Recommended Practice No. 34R-05. Spire’s evaluation included quantification and pricing of major equipment and facilities, and identification of potential schedule risks associated with procurement. PG&E and Processes Unlimited utilized Spire’s findings to validate existing cost estimates, negotiate contracts and schedule procurement activities.