Spire provided cost estimating and schedule risk analysis services for Pacific Gas and Electric’s K-2 Compressor Replacement Project at the Delevan Compressor Station in Delevan, California. Spire developed a preliminary cost estimate and supporting basis of estimate in accordance with the Association for Advancement of Cost Engineering International’s (AACEI) Recommended Practice No. 34R-05. Spire’s evaluation included quantification and pricing of major equipment and facilities, and identification of potential schedule risks associated with procurement. PG&E and Processes Unlimited utilized Spire’s findings to validate existing cost estimates, negotiate contracts and schedule procurement activities.