Mica Generating Station, Units 5 and 6

Contact Us




Mica Generating Station, Units 5 and 6

Client Confidential
Location British Columbia, Canada
Scope Of Work Construction Claims, Request for Equitable Adjustment (REA)
Schedule 2015

Project Detail


The $800 million MICA Generating Station Units 5 and 6 Project, located on the Columbia River, approximately 150 kilometers north of the City of Revelstoke, consists of the installation of two 500-megawatt generating units. The units will add approximately 1,000 megawatts of generation capacity, enough to power 80,000 homes in British Columbia during peak periods of demand. Unit 5 was in full operation in October 2014 and Unit 6 in October 2015. Spire was hired by one of the main contractors tasked with the design, supply, and installation of the turbines and generators to prepare a Request for Equitable Adjustment (REA) to substantiate issues and costs related to construction of Units 5 and 6 of the Mica Generating Station project. Spire’s consultants analyzed the as planned and as-built project schedules to develop a Request for Time Extension and quantify damages.